  591. Cost and schedule data are usually integrated because:
  A. optimized project cash flow can affect financial requirements
  B. they provide MIS with an integrated system to produce reports
  C. they control escalation allowances
  D. they account for omissions in the definitive estimate
  E. they predict future performance
  ANS: E
  
  592. In which of the following organization(s) does the Functional Manager have the LEAST authority?
  A. coordinator
  B. weak matrix
  C. strong matrix
  D. functional
  E. expediter
  ANS: C
  
  593. When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
  A. task
  B. level of effort
  C. sub-task
  D. project
  E. work package
  ANS: E
  
  594. An effective Project Manager does not share project _____ with the team members.
  A. Vision
  B. responsibility
  C. solution to problems
  D. accountability
  E. status
  ANS: D
  
  595. Parametric estimates are based on variables such as:
  A. Detailed planning and cost restraints.
  B. Physical characteristics and historical data.
  C. The WBS and similar projects.
  D. Project objectives and manpower allocations.
  E. Precise measurements and multiple inputs.
  ANS: B
  
  596. The time necessary to complete a project is called the _______ of a project.
  A. Implementation Time
  B. Life Cycle
  C. Operation Time
  D. Critical Path
  E. Completion Phase
  ANS: B
  
  597. The Communications Management Plan should contain the following:
  A. Communications policy
  B. Communications media
  C. Reporting channels
  D. Selection of appropriate media to meet specific needs
  E. All of the above
  ANS: E
  
  598. The Cost Performance Index (CPI) measures:
  A. cost of work performed vs planned costs.
  B. work performed vs cost of work performed.
  C. work performed vs planned work.
  D. direct costs vs indirect costs.
  E. floating costs vs. sunk costs.
  ANS: B
  
  599. The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.
  A. budget, schedule
  B. quality requirements, schedule
  C. size, type of industry
  D. nature, size
  E. project manager, sponsor
  ANS: D
  
  600. Which theory(s) prescribes a form of participative management?
  A. theory X
  B. theory Y
  C. theory Z
  D. A or B
  E. B or C
  ANS: B
  
  